# Section 889 in federal contracts: the covered telecommunications and video surveillance prohibition (FAR 52.204-24, 52.204-25 and 52.204-26), explained

Section 889 bars agencies from buying covered Chinese telecommunications and video surveillance equipment and from contracting with companies that use it anywhere. The FAR carries it into every solicitation through two representations and a reporting clause.

Explainer · Cross-sector · Economics & Procurement. Published November 14, 2026. Last reviewed November 14, 2026.

## At a glance

- Since August 13, 2019, agencies may not buy equipment, systems or services that use covered telecommunications equipment or services as a substantial or essential component or as critical technology [2].
- Since August 13, 2020, agencies may not contract with an entity that uses such equipment, whether or not the use is in performance of a federal contract [2].
- Offerors represent whether they provide or use covered equipment after a reasonable inquiry, which does not require an internal or third-party audit [7][1].
- Contractors report covered equipment found during performance within one business day, with a follow-up within 10 business days [6].
- A FAR overhaul proposal published June 23, 2026 (91 FR 37550) would move the rules to FAR part 40 and one consolidated clause; as checked on November 14, 2026 it was still a proposal [8][1].

Section 889 of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232) sets two prohibitions on executive agencies, and the Federal Acquisition Regulation (FAR) carries them into contracts through one clause and two representations [6]. The second prohibition has the wider reach: it turns on what equipment a company uses anywhere in its business, rather than solely on what it delivers to the government [2]. Any organization that bids for a contract under the FAR, whatever its industry, meets the 52.204-25 clause in every solicitation and contract [4].

The rules are in FAR subpart 4.21 and the clauses at 52.204-24, 52.204-25 and 52.204-26. A June 2026 proposal would move and rewrite them, so the status below is as checked on November 14, 2026.

## The two prohibitions and their dates

- **Buying (from August 13, 2019):** agencies may not procure or obtain, or extend or renew a contract to procure or obtain, any equipment, system or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system [2].
- **Contracting with users (from August 13, 2020):** agencies may not enter into, extend or renew a contract with an entity that uses any equipment, system or service that uses covered telecommunications equipment or services in those ways. The FAR states that this applies regardless of whether the use is in performance of work under a federal contract [2].

Two exceptions apply to both: a service that connects to the facilities of a third party, such as backhaul, roaming or interconnection arrangements, and telecommunications equipment that cannot route or redirect user data traffic or permit visibility into user data or packets it handles [2].

## What “covered” means

The covered foreign country is the People’s Republic of China [1]. Covered telecommunications equipment or services means [1]:

- telecommunications equipment produced by two named companies, or their subsidiaries or affiliates;
- for public safety, security of government facilities, physical security surveillance of critical infrastructure and other national security purposes, video surveillance and telecommunications equipment produced by three further named companies, or their subsidiaries or affiliates;
- telecommunications or video surveillance services provided by those entities or using that equipment; and
- equipment or services from an entity the Secretary of Defense, in consultation with the Director of National Intelligence or the FBI Director, reasonably believes is owned or controlled by, or otherwise connected to, the government of a covered foreign country.

A substantial or essential component is any component necessary for the proper function or performance of a piece of equipment, system or service. Critical technology is defined by reference to export control and similar lists, including the U.S. Munitions List, controlled items on the Commerce Control List and emerging and foundational technologies controlled under the Export Control Reform Act of 2018 [1]. Prohibitions on purchases from the named companies, including known subsidiaries and affiliates, are recorded in the System for Award Management (SAM) [2].

## The paperwork: two representations and a disclosure

Contracting officers must put 52.204-26 in all solicitations, 52.204-24 in all solicitations for contracts and in notices of intent to place orders under indefinite delivery contracts, and the 52.204-25 clause in all solicitations and contracts [4].

- **52.204-26** asks the offeror to review the SAM list of excluded parties for covered telecommunications, then represent whether it does or does not provide covered equipment or services to the government, and, after a reasonable inquiry, whether it does or does not use them, or use anything that uses them [7].
- **52.204-24** is completed only where the offeror answered “does” in 52.204-26 (or the matching paragraphs of 52.212-3 for commercial products and services). An offeror that answers “will” provide or “does” use must disclose the producer, the equipment or service, and an explanation of the proposed use and why it may be permissible [3][5].

A “reasonable inquiry” is an inquiry designed to uncover any information in the entity’s possession about the identity of the producer or provider of covered equipment or services it uses, and it excludes the need for an internal or third-party audit [1]. Contracting officers may rely on a “does not” or “will not” answer unless they have reason to question it [3].

## During performance: the one-business-day report

If a contractor identifies covered equipment or services used as a substantial or essential component or as critical technology during contract performance, or is told of it by a subcontractor or any other source, it must report to the contracting officer; Defense Department contractors report at dibnet.dod.mil [6]. The clause sets two steps [6]:

- **Within one business day** of identification or notification: contract and order numbers, supplier name and identifiers if known, brand, model number, item description and any readily available information about mitigation.
- **Within 10 business days** of that first report: any further mitigation information, a description of the efforts made to prevent use or submission of covered equipment or services, and the additional efforts planned to prevent it in future.

The contractor must insert the substance of 52.204-25 in all subcontracts, including those for commercial products and services, except paragraph (b)(2), the prohibition on contracting with users [6].

## Waivers

Agency heads could grant one-time waivers, but only for periods not extending beyond August 13, 2021 for the buying prohibition and August 13, 2022 for the contracting-with-users prohibition, with a phase-out plan and notices to Congress [3]. The Director of National Intelligence may also provide a waiver if the Director determines it is in the national security interests of the United States [3].

## The June 2026 proposal to move and rewrite the rules

On June 23, 2026 the FAR Council published a proposed rule under its Revolutionary FAR Overhaul covering FAR parts 1, 2, 4, 33, 39, 40, 52 and 53 (91 FR 37550), with comments due July 23, 2026 [8]. It would move security prohibitions and exclusions, with their provisions and clauses, from part 4 to part 40, create a single “do not buy” list, and consolidate five provisions into one and seven clauses into one [8]. For section 889 it proposes to [8]:

- clarify what “produced” means in the definition of covered telecommunications equipment or services;
- define critical technology as a technology in whose absence a system cannot adequately operate or function;
- add definitions of system, telecommunications equipment and services, and video surveillance equipment and services;
- state that commercial sales, maintenance, testing services, warranty services and employees’ use of personal equipment are not individually considered use of covered equipment or services; and
- apply one reasonable inquiry standard across the prohibitions, stating that no internal or third-party audit is needed.

One passage of the proposal’s preamble refers to section 889 of the National Defense Authorization Act for Fiscal Year 2018, while the current FAR clauses, and the proposal’s own regulatory text, name the John S. McCain National Defense Authorization Act for Fiscal Year 2019, Pub. L. 115-232 [8][6]; we use the clauses’ citation. As checked on November 14, 2026, the eCFR text current to November 12, 2026 still carries subpart 4.21 and the three clauses described above [1][6].

## Where the cost falls

In our view, the expensive part for a regulated organization that sells to government is the “use” representation, because it covers the whole enterprise: branch and office networks, building cameras and the managed services that run them. A current inventory of network and video equipment, with producer names, is what lets a company answer 52.204-26 after a reasonable inquiry, and the same inventory supports the one-business-day report if something turns up later. The proposed rewrite would narrow some of the open questions without removing the prohibition, so the inventory work does not depend on how the proposal ends.

This explainer describes the regulation; it is not legal advice, and organizations should confirm with counsel how it applies to their contracts.

Moraph’s teams help organizations with work like this. [See our solutions](https://www.moraph.com/solutions).

## Sources

1. Electronic Code of Federal Regulations (Office of the Federal Register). FAR 4.2101, Definitions (subpart 4.21), eCFR text up to date as of November 12, 2026. <https://www.ecfr.gov/current/title-48/section-4.2101> Checked November 14, 2026.
2. Electronic Code of Federal Regulations (Office of the Federal Register). FAR 4.2102, Prohibition, eCFR text up to date as of November 12, 2026. <https://www.ecfr.gov/current/title-48/section-4.2102> Checked November 14, 2026.
3. Electronic Code of Federal Regulations (Office of the Federal Register). FAR 4.2103, Procedures, and 4.2104, Waivers, eCFR text up to date as of November 12, 2026. <https://www.ecfr.gov/current/title-48/chapter-1/subchapter-A/part-4/subpart-4.21> Checked November 14, 2026.
4. Electronic Code of Federal Regulations (Office of the Federal Register). FAR 4.2105, Solicitation provisions and contract clause, eCFR text up to date as of November 12, 2026. <https://www.ecfr.gov/current/title-48/section-4.2105> Checked November 14, 2026.
5. Electronic Code of Federal Regulations (Office of the Federal Register). FAR 52.204-24, Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021), eCFR text up to date as of November 12, 2026. <https://www.ecfr.gov/current/title-48/section-52.204-24> Checked November 14, 2026.
6. Electronic Code of Federal Regulations (Office of the Federal Register). FAR 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021), eCFR text up to date as of November 12, 2026. <https://www.ecfr.gov/current/title-48/section-52.204-25> Checked November 14, 2026.
7. Electronic Code of Federal Regulations (Office of the Federal Register). FAR 52.204-26, Covered Telecommunications Equipment or Services—Representation (OCT 2020), eCFR text up to date as of November 12, 2026. <https://www.ecfr.gov/current/title-48/section-52.204-26> Checked November 14, 2026.
8. Office of Federal Procurement Policy, Department of Defense, General Services Administration and NASA (FAR Council), Federal Register (via GovInfo). Federal Acquisition Regulation: Revolutionary Federal Acquisition Regulation Overhaul Parts 1, 2, 4, 33, 39, 40, and 53, proposed rule, FR Doc. 2026-12559 (91 FR 37550, June 23, 2026). <https://www.govinfo.gov/content/pkg/FR-2026-06-23/html/2026-12559.htm> Checked November 14, 2026.

Published: November 14, 2026
Canonical URL: <https://insights.moraph.com/far-section-889-covered-telecommunications-prohibition-explained>
Publisher: Moraph Insights